9. Building fireline downhill with fire below. Three firefighters use tools to dig fireline down a steep slope covered in grass and brush.  Large flames are below them as the fire burns uphill.

9. Building fireline downhill with fire below.

Building fireline downhill requires special attention to safety factors because of the potential for rapid uphill fire spread. This Watch Out depicts firefighters building fireline downhill without first mitigating the existing hazards.

Read about all 18 Watch Out Situations..

Downhill fireline construction is hazardous in steep terrain, fast-burning fuels, or rapidly changing weather. Downhill fireline construction should not be attempted unless there is no tactical alternative. When building downhill fireline:

  • Crew supervisor(s) and fireline overhead must discuss assignments prior to committing personnel. Qualified, responsible overhead individuals such as a Task Force Leader (TFLD) or an Incident Commander Type 4 (ICT4) at minimum, will stay with resources until the job is completed.
  • Decisions about downhill fireline construction will be made only after proposed fireline has been scouted by supervisor(s) of involved crew(s).
  • Lookouts, Communications, Escape Routes, and Safety Zones (LCES) will be coordinated for all personnel involved. This includes verifying:
    • Crew supervisors are in direct contact with lookout(s) who can see the fire.
    • Communication is established between crews.
    • Rapid access to safety zones is ensured in case fire crosses below crews.
  • Direct attack will be used whenever possible; if not possible, the fireline should be completed between anchor points before being fired out.
  • Fireline will not lie in or adjacent to a chute or chimney.
  • Starting point will be anchored for crews building fireline down from the top.
  • Bottom of the fire will be monitored; if the potential exists for the fire to spread, action will be taken to secure the fire edge.
  • Before carrying fire with you, ensure it can be done safely.

 

Last Modified / Reviewed:

Have an idea or feedback?

Share it with the NWCG 6MFS Subcommittee.


Follow NWCG on Twitter and Facebook

NWCG Latest Announcements

The Incident Position Standards and Next Generation Position Task Book are now available for Status/Check-In Recorder (SCKN)

Date: August 27, 2024
Contact: Incident Planning Subcommittee 

NWCG is excited to announce that the NWCG Incident Position Standards for Status/Check-In Recorder, PMS 350-32, NWCG Position Task Book for Status/Check-In Recorder (SCKN), PMS 311-32, and Checking In Resources Customer Service Job Aid, J-111 are now available.

The Performance Support Package, which for SCKN includes the Incident Position Standards, Next Generation Position Task Book, and job aid were developed through the Incident Performance and Training Modernization (IPTM) effort. The Performance Support Package will support trainees, those qualified in the position, and evaluators.

References:

NWCG Status/Check-In Recorder Position Page

NWCG Incident Position Standards for Status/Check-In Recorder, PMS 350-32

NWCG Position Task Book for Status/Check-In Recorder (SCKN), PMS 311-32

Checking In Resources Customer Service Job Aid, J-111

The Next Generation Position Task Book and Incident Position Standards are now available for Safety Officer, Field (SOFF)

Date: July 26, 2024
Contact: Risk Management Committee 

NWCG is excited to announce that the NWCG Incident Position Standards for Safety Officer, Field, PMS 350-81 and NWCG Position Task Book for Safety Officer, Field (SOFF), PMS 311-81 are now available.

The Safety Officer, Field (SOFF) is responsible for monitoring operations on an incident from a risk management perspective to provide for the welfare of incident resources and the public. The new Incident Position Standards and Next Generation Position Task Book are developed through the Incident Performance and Training Modernization (IPTM) effort.

References:

NWCG Safety Officer, Field (SOFF) Position

NWCG Incident Position Standards for Safety Officer, Field, PMS 350-81

NWCG Position Task Book for Safety Officer, Field (SOFF), PMS 311-81

Updated NWCG Standards for Electronic Documentation (eDoc), PMS 277

Date: July 25, 2024
Contact: Incident Planning Subcommittee 

The Incident Planning Subcommittee has updated the NWCG Standards for Electronic Documentation (eDoc), PMS 277.

The NWCG Standards for Electronic Documentation (eDoc) establishes the standards for collection and retention of records on wildland fires. This July 2024 update will provide incident management teams the most current standards required to maintain incident records and submit them to host units at the close of an incident.

References:

NWCG Standards for Electronic Documentation (eDoc), PMS 277

eDoc Box Directory (zip file)

NWCG Off-Highway Vehicle Typing Standard Request for Comment

Date: July 24, 2024
Contact: Mobile Fire Equipment Subcommittee 

The Mobile Fire Equipment Subcommittee has released Equipment Bulletin 24-002 NWCG Off-Highway Vehicle (OHV) Typing Standard - Request for Comment. This bulletin outlines the proposed NWCG OHV typing standard, as well as the business need for establishing the standard. Comments on the proposed standard will be accepted through August 15th using the comment form linked below.

References:

ETC-EB-2024-02: NWCG Off-Highway Vehicle (OHV) Typing Standard - Request for Comment

NWCG Off-Highway Vehicle (OHV) Typing Standard Comment Form