SYSTEM:  Helicopter Operations, Personnel (Government)

Sub-System Hazards Pre-Mitigation Mitigation Post-Mitigation

Probability

Severity

Risk Level

Probability

Severity

Risk Level

Policy Operational and mission goals during all-hazard assignments may be unstated or unclear and may conflict with interagency standards and policy

Likely

Critical

Extremely High

Adequate in-brief and dissemination of Commander's intent. Clarification of scope of authority and policy in place.  Adhere to interagency policy, procedures and guidelines (e.g., NSHO). If unable to perform duties utilizing interagency policy, perform a separate risk assessment with appropriate approval sign off. Ensure personnel are working within the scope of their employment. Implementation of Aviation Doctrine may further mitigate conflicts between direction and policy.

Possible

Critical

High

Training Unable to bring seasonals on early enough to provide all the required training prior to sending on incidents

Almost Certain

Critical

Extremely High

Ensure line officers are committed to providing adequate time and funding to develop personnel as necessary.

Possible

Critical

High

Lack of Crew Resource Management (CRM)

Likely

Critical

Extremely High

Provide adequate time for training and provide time for Modules to develop CRM prior to field season.  Provide training in CRM for Modules annually. Brief/debrief, maintain positive attitude.

Possible

Critical

High

Human Factors Fatigue/burnout due to incident duration as well as year-round All Risk incident support

Likely

Critical

Extremely High

Adhere to work/rest guidelines. Monitor fatigue levels of crews. Rotate personnel and helicopter programs to manage fatigue and burnout. Manage number and duration of assignments. Ensure adequate time off and provide quality R and R while on assignments.

Possible

Critical

High

Acceptance of high-risk missions as normal

Likely

Catastrophic

Extremely High

Review risk assessment and existing policy/procedures, brief/debrief with all personnel and utilize risk management tools to include Go-No-Go Checklists. Educate personnel on the hazards of normalization of risk and complacency. Mission decision made at appropriate level. Must have better communication and collaboration between Operations and Aviation.

Unlikely

Catastrophic

High

High workload for Maintenance Inspectors may compromise their ability to perform thorough inspections.  Standard inspections criteria not followed consistently among agencies or regions

Likely

Critical

Extremely High

Increase amount of personnel available to perform the duties of Maintenance Inspector in proportion with span of control. Ensure inspection standards are developed and maintained by agencies.

Unlikely

Critical

Medium

Conflicting personalities resulting in hazardous attitudes

Possible

Critical

High

If individuals cannot professionally resolve differences, managers and supervisors must intervene immediately. Brief/debrief, employ CRM, provide honest and objective feedback, maintain positive attitude. Maintain professionalism and mission focus at all times.

Unlikely

Critical

Medium

 

Download the Word version (docx) of this information and the Risk Assessment Matrix (pdf) to use with the Risk Assessment Worksheet (docx).

 

 

Modified / Reviewed:

NWCG Latest Announcements

The Incident Position Standards and Next Generation Position Task Book are now available for Status/Check-In Recorder (SCKN)

Date: August 27, 2024
Contact: Incident Planning Subcommittee 

NWCG is excited to announce that the NWCG Incident Position Standards for Status/Check-In Recorder, PMS 350-32, NWCG Position Task Book for Status/Check-In Recorder (SCKN), PMS 311-32, and Checking In Resources Customer Service Job Aid, J-111 are now available.

The Performance Support Package, which for SCKN includes the Incident Position Standards, Next Generation Position Task Book, and job aid were developed through the Incident Performance and Training Modernization (IPTM) effort. The Performance Support Package will support trainees, those qualified in the position, and evaluators.

References:

NWCG Status/Check-In Recorder Position Page

NWCG Incident Position Standards for Status/Check-In Recorder, PMS 350-32

NWCG Position Task Book for Status/Check-In Recorder (SCKN), PMS 311-32

Checking In Resources Customer Service Job Aid, J-111

The Next Generation Position Task Book and Incident Position Standards are now available for Safety Officer, Field (SOFF)

Date: July 26, 2024
Contact: Risk Management Committee 

NWCG is excited to announce that the NWCG Incident Position Standards for Safety Officer, Field, PMS 350-81 and NWCG Position Task Book for Safety Officer, Field (SOFF), PMS 311-81 are now available.

The Safety Officer, Field (SOFF) is responsible for monitoring operations on an incident from a risk management perspective to provide for the welfare of incident resources and the public. The new Incident Position Standards and Next Generation Position Task Book are developed through the Incident Performance and Training Modernization (IPTM) effort.

References:

NWCG Safety Officer, Field (SOFF) Position

NWCG Incident Position Standards for Safety Officer, Field, PMS 350-81

NWCG Position Task Book for Safety Officer, Field (SOFF), PMS 311-81

Updated NWCG Standards for Electronic Documentation (eDoc), PMS 277

Date: July 25, 2024
Contact: Incident Planning Subcommittee 

The Incident Planning Subcommittee has updated the NWCG Standards for Electronic Documentation (eDoc), PMS 277.

The NWCG Standards for Electronic Documentation (eDoc) establishes the standards for collection and retention of records on wildland fires. This July 2024 update will provide incident management teams the most current standards required to maintain incident records and submit them to host units at the close of an incident.

References:

NWCG Standards for Electronic Documentation (eDoc), PMS 277

eDoc Box Directory (zip file)

NWCG Off-Highway Vehicle Typing Standard Request for Comment

Date: July 24, 2024
Contact: Mobile Fire Equipment Subcommittee 

The Mobile Fire Equipment Subcommittee has released Equipment Bulletin 24-002 NWCG Off-Highway Vehicle (OHV) Typing Standard - Request for Comment. This bulletin outlines the proposed NWCG OHV typing standard, as well as the business need for establishing the standard. Comments on the proposed standard will be accepted through August 15th using the comment form linked below.

References:

ETC-EB-2024-02: NWCG Off-Highway Vehicle (OHV) Typing Standard - Request for Comment

NWCG Off-Highway Vehicle (OHV) Typing Standard Comment Form